The Sharp Group -  Projects - Recently Completed Blog

Find the latest news, construction updates, scheduling, and photos here.

Fort Frances, Ontario to International Falls, Minnesota - Border Crossing

February 23, 2026
Work on the border crossing located in Fort Frances, Ontario consisted of The Sharp Group removing the old railway, completing granular work, and paving. 
 

MNR 20583 - Longlegged River Bridge

February 23, 2026
The Sharp Group began construction activities on this MNR forestry access bridge in September 2025. A new 80' bridge was installed on Longlegged Lake Road, Northwest of Ear Falls, Ontario. 
Continue reading...
 

Our Lady of The Way School - Sidewalk and Bus Lane

February 23, 2026
The Sharp Group completed work at Our Lady of The Way School in the summer of 2025. The work consisted of cast-in-place sidewalks and curbs, paving, and drainage work.
Continue reading...
 

2025-6004 Eleanor Bay Bridge & McCool River Bridge

February 23, 2026
This project consisted of two bridges requiring deck rehabilitations. One bridge was located on Highway 621 and the other was located on Highway 613. Repairs were ongoing throughout the summer and were completed by September 2025.
Continue reading...
 

2024-6018 Ney Creek Culvert

February 23, 2026
In July 2024 The Sharp Group commenced work at Ney Creek Culvert site, located West of Marathon, Ontario. A concrete box culvert was installed in place of the existing structure and work was completed in late August 2024.

Continue reading...
 

2022-6012 Cameron Creek Culvert

February 23, 2026
The Sharp Group commenced work at Cameron Creek Culvert, located on Highway 11, in August of 2023. The existing culvert was removed and replaced with two large multi-plate culverts.
Continue reading...
 

2022-6023 Sandy Creek

April 24, 2024
The Sharp Group commenced work on site at Sandy Creek jobsite in late June 2023. The existing structures were removed and replaced with precast concrete box culverts.
Continue reading...
 

2022-6002 Manitou Creek

November 10, 2022
Work began at Manitou Creek Culvert site at the beginning of July 2022. The Sharp Group lined the existing box culvert.
Continue reading...
 

2022-6016 Blackwater Tributary

November 10, 2022
Work commenced in the Municipality of Greenstone, at Blackwater Tributary Culvert site, on June 01, 2022. The Sharp Group installed a precast rigid frame box culvert. Work on site was completed by mid July.
Continue reading...
 

2021-6055 Black Sturgeon

November 10, 2022
The Sharp Group commenced work at Black Sturgeon Lake Bridge on August 16, 2022. Work began on removing the existing modular bridge. After removal of existing structure was completed, a new modular bridge was installed. 
Continue reading...