The Sharp Group -  Projects - Recently Completed Blog

Find the latest news, construction updates, scheduling, and photos here.

2019-6005 Namakan River Bridge

November 25, 2021
The Sharp Group traveled to Flanders Road at Lady Rapids South of Highway 11 in July of 2019. Work commenced on site at Namakan River in August of 2019. A 160' modular bridge was used to replace the existing structure. Work on site was completed by the beginning of October 2019.
 

2019-6251 Hawkeye Lake

November 25, 2021
The Sharp Group commenced removal of the existing structure at Hawkeye Lake East Road in September 2019. A small modular bridge was installed. The project was completed in October 2019.
Continue reading...
 

Shoal Lake 40 Repair

November 25, 2021
The Sharp Group traveled to Shoal Lake 40 Road, in Shoal Lake, for a repair job in the middle of October 2019. The existing structure was re-decked. 
Continue reading...
 

Ahren's Bridge

September 25, 2019
The Sharp Group commenced work on removing and replacing this structure in early May of 2019. The structure is located on Sturgeon Creek Road in Chapple Township (Barwick, On). The existing structure was removed and replaced with a 27.2 meter, single span, concrete box girder, with cast in place deck. Work was completed at this site mid July 2019. 
Continue reading...
 

Coker River Bridge #18-09

August 29, 2019
The Sharp Group commenced work on Coker River Bridge, located North of Kenora Ontario, on Coker Road, at the beginning of July 2019. The existing structure was removed and replaced with a bailey bridge. Work on site was completed at the end of July 2019.
Continue reading...
 

2018-6252 Pinewood River Bridge #1

May 1, 2019
The Sharp Group began work at Vargyas Road: South of Gouliquer Road between Hwy 617 and Hwy 619, in early October of 2018. The existing structure was removed and a new hi-beam bridge was installed in it's place. Work was completed in late October 2018. 
Continue reading...
 

2018-6021 Hutchinson Bridge Repair

May 1, 2019
The Sharp Group commenced work on repairing a modular panel bridge, located West of  Hwy 105 and Hwy 609 junction, in late November of 2018. The repairs were completed in late December 2018. 
Continue reading...
 

Design Build 2017-6018, Culvert Replacements

October 29, 2018
The Sharp Group installed a triple barrel culvert at Pinewood River Tributary #2 located on Highway 617. Triple barrel culverts were also installed at Maximillian and Sims culverts', located on Highway 71. A twin barrel culvert was used to replace the existing culvert at Toby Hill, also located on Highway 71. Located on Highway 11, Dilke Creek culvert was removed and replaced with a single barrel pipe culvert. Work commenced on this project late May 2018, and was completed September 2018.
Continue reading...
 

Pinewood River Bridge, Highway 617

October 29, 2018
The Sharp Group began removal of the existing bridge in May of 2018. A two lane 100' modular panel bridge was installed in it's place. Work was completed in July 2018.
Continue reading...
 

Shoal Lake Aqueduct Project

October 29, 2018
The Sharp Group commenced work on the installation of the 100' modular panel, single lane bridge in April 2018. Work was completed mid-August 2018.
Continue reading...