Pic River Hydro Dam, White River, Ontario

March 30, 2016
Bridge repairs were done on the Pic River Hydro Dam Bridge in White River, Ontario in June, 2015.  This time sensitive project saw the replacement of the bridge with a 100 & 110 ft. permanent structures with 3 temporary works.  Project was completed in a 3 week time frame.  The temporary structure will be removed in March.
 

Munroe & Hastie, Devlin, Ontario - 2015

March 30, 2016
Project began in March, 2015 and was completed in July, 2015, well ahead of the deadlines.  Two bridges, located north of Devlin on Hwy 613N, were replaced with box beam concrete structures, approximately 23 meters in length each.

Continue reading...
 

Off Lake Bridge, Emo, Ontario - 2014

November 4, 2014
The Sharp Group began work on the Off Lake Bridge, located north of Emo, Ontario on Hwy 615, on September 3, 2014. A completion date of November 7, 2014 saw them well ahead of schedule. This job consisted of replacing an existing wooden pile, timber deck with a concrete overlay bridge, with a brand new 100 ft. double-lane Mabey Modular Bridge.

Continue reading...
 

Little Grassy Culvert, Bergland, Ontario - 2014

November 4, 2014
The aging culvert located on Hwy 600, west of Hwy 621, near Bergland, Ontario required replacing.  Three galvanized pipe culverts were replaced with a precast culvert structure.  It was critical to meet the road closure deadline of 6 days, since the detour was long. The Sharp Group was able to complete this job in the time allotted.

Continue reading...
 

Little Grassy River Bridge, Bergland, Ontario - 2014

November 4, 2014
The Sharp Group started work on the Little Grassy River Bridge, North of Hwy 600, located next to the Bergland Store commencing on July 14th, 2014.  The timber pile with wooden deck, double-lane bridge was replaced with a new 100' double-lane Mabey Modular Bridge.  A detour route was required during this construction.  Final paving was completed in August, 2014, ahead of schedule.

Continue reading...
 

Yongeberg Bridge, Bergland, Ontario - 2014

November 4, 2014
This bridge is located east of Bergland, Ontario, on Hwy 600.  A 120ft double-lane modular bridge replaced the aging timber pile/wooden deck bridge.  The Yongeberg project was completed in July, 2014.

Continue reading...
 

Seven Mile Bridge, Fort Frances, Ontario - 2014

November 4, 2014
In mid-May work began on the Seven Mile Bridge located on Rainy Lake, east of Fort Frances, Ontario.  A multi-span bridge was removed and replaced with a new clear span 120ft concrete box girder bridge.  Traffic density was high at this location and as the smooth flow of traffic was ensured.  Completion took place mid-October, 2014.

Continue reading...
 

Panko Narrow Bridge, Manitoba

November 4, 2014
The Sharp Group constructed a new 210 ft. Acrow Panel Bridge at Panko Narrows Bridge job site.  The bridge work in this northern Manitoba location was completed in harsh winter conditions in March of 2014.  It is important to note that the construction of this bridge assists in extending the winter road access in northern Manitoba

Continue reading...
 

North Current River, Thunder Bay, Ontario

November 4, 2014
The collapse of a culvert on Hwy 527 on the North Current River created an emergency situation requiring immediate replacement. A temporary modular bridge was installed for traffic while work on the 12.5 metre clear span, multi-plated arch culvert was completed. This project was completed quickly and efficiently within the time constraints.

Continue reading...
 

Pelican River Bridge

August 9, 2013
The Sharp Group commenced work at the Pelican River job site, Northwest of Dryden on August 12, 2013. This job consisted of replacing an existing structure with a modular bridge on Haukeness Road, off of Highway 605,

The newly constructed modular bridge over the Pelican River was completed in October, 2013.


Continue reading...