Pelican River Bridge

Posted by Sharp Bridges on Friday, August 9, 2013, In : Jobsite Updates 
The Sharp Group commenced work at the Pelican River job site, Northwest of Dryden on August 12, 2013. This job consisted of replacing an existing structure with a modular bridge on Haukeness Road, off of Highway 605,

The newly constructed modular bridge over the Pelican River was completed in October, 2013.


Continue reading ...
 

Rainy River Tributary Update

Posted by The Sharp Group on Wednesday, August 15, 2012, In : Jobsite Updates 
Removal of existing concrete culvert and construction of modular panel bridge is currently in progress at the Rainy River Tributary bridge site located outside of Fort Frances, Ontario.  Road closure for the improvements to the culvert commenced August 9th and tentative date for road re-opening is slated for August 30th.  Detour access around the job site via Oakwood Road and Bone Road.  
Continue reading ...
 

Work at Wolf Creek Jobsite Begins

Posted by The Sharp Group on Monday, July 16, 2012, In : Jobsite Updates 
Work at the Wolf Creek jobsite South of Emo on Colonization road began today. This modular bridge is part of the Rainy River Tributary project, which also includes a cement culvert on Colonization road just outside of Fort Frances.
Continue reading ...