The Sharp Group -  Projects - Recently Completed Blog

Find the latest news, construction updates, scheduling, and photos here.

Ahren's Bridge

September 25, 2019
The Sharp Group commenced work on removing and replacing this structure in early May of 2019. The structure is located on Sturgeon Creek Road in Chapple Township (Barwick, On). The existing structure was removed and replaced with a 27.2 meter, single span, concrete box girder, with cast in place deck. Work was completed at this site mid July 2019. 
 

Coker River Bridge #18-09

August 29, 2019
The Sharp Group commenced work on Coker River Bridge, located North of Kenora Ontario, on Coker Road, at the beginning of July 2019. The existing structure was removed and replaced with a bailey bridge. Work on site was completed at the end of July 2019.
Continue reading...
 

2018-6252 Pinewood River Bridge #1

May 1, 2019
The Sharp Group began work at Vargyas Road: South of Gouliquer Road between Hwy 617 and Hwy 619, in early October of 2018. The existing structure was removed and a new hi-beam bridge was installed in it's place. Work was completed in late October 2018. 
Continue reading...
 

2018-6021 Hutchinson Bridge Repair

May 1, 2019
The Sharp Group commenced work on repairing a modular panel bridge, located West of  Hwy 105 and Hwy 609 junction, in late November of 2018. The repairs were completed in late December 2018. 
Continue reading...
 

Design Build 2017-6018, Culvert Replacements

October 29, 2018
The Sharp Group installed a triple barrel culvert at Pinewood River Tributary #2 located on Highway 617. Triple barrel culverts were also installed at Maximillian and Sims culverts', located on Highway 71. A twin barrel culvert was used to replace the existing culvert at Toby Hill, also located on Highway 71. Located on Highway 11, Dilke Creek culvert was removed and replaced with a single barrel pipe culvert. Work commenced on this project late May 2018, and was completed September 2018.
Continue reading...
 

Pinewood River Bridge, Highway 617

October 29, 2018
The Sharp Group began removal of the existing bridge in May of 2018. A two lane 100' modular panel bridge was installed in it's place. Work was completed in July 2018.
Continue reading...
 

Shoal Lake Aqueduct Project

October 29, 2018
The Sharp Group commenced work on the installation of the 100' modular panel, single lane bridge in April 2018. Work was completed mid-August 2018.
Continue reading...
 

Highways 619 and 621, Culvert Replacements

October 29, 2018
The Sharp Group began work on a project consisting of 3 individual sites. Gerhard and Petersons' existing culverts located on Highway 619, were replaced with twin concrete box culverts. The culvert replacement at Brusvine located on Highway 621, consisted of a multi plate 4m culvert being installed. Work commenced on this project in early July of 2017 and was completed by the end of November 2017.
Continue reading...
 

Gullwing River Bridge

October 29, 2018
The Sharp Group commenced work on installing the 100' single lane modular panel bridge, located on Henderson Loop Road 1 km west of Highway 665, in late October 2017. The new bridge was completed late November 2017.
Continue reading...
 

Kishkakoesis Bridge, Brown Rd off Highway 619

October 29, 2018
Bridge removal began on Brown Road in early February of 2017. A double lane modular panel bridge was installed and work completed by March 2017.
Continue reading...